A roofing estimate template built around squares.

Tear-off, decking, underlayment, and the flashing details that decide whether a roof quote holds up once the old material is off.

Get the roofing estimate template

A working spreadsheet, not a picture of one. The totals, overhead, and margin are live formulas. We email it over, so no download to lose track of.

One email with the template attached. We will not pass your address on.

A roof estimate is one measurement with three corrections applied to it. The measurement is squares. The corrections are pitch, waste, and whatever is underneath the old material. A template that captures only the first one will be wrong on most roofs.

The template

SectionLine itemUnitWhat decides it
MeasureRoof areaSquaresFootprint corrected for pitch
MeasurePitch factorMultiplier6/12 is about 1.12, 12/12 about 1.41
MeasureWaste allowancePercent7-10% simple gable, 15%+ cut up
RemovalTear-offSquares x layersLayer count, verified not assumed
RemovalDisposalContainerWeight, which doubles with layers
DeckDecking replacementPer sheetUnit price agreed in advance
DeckUnderlaymentSquaresSynthetic or felt
DeckIce and water shieldLinear feetEaves and valleys, per code
FieldShingles or panelsSquaresMaterial and profile
FieldStarter stripLinear feetEave and rake length
FieldRidge capLinear feetRidge and hip length
EdgesDrip edgeLinear feetPerimeter
EdgesValley treatmentLinear feetOpen or closed
DetailsStep and counter flashingLinear feetWalls, chimneys
DetailsPipe boots and ventsCountPenetration count
DetailsVentilationLinear feet or countRidge vent, or the code item that grows the job
AccessSteep or high-access chargeSquaresAbove 7/12, staging and harnesses
TotalsJob cost, overhead, profitSum, percent, percentKept as three separate lines

The two lines that prevent arguments

Decking replacement is the honest unknown on every tear-off. You cannot see the deck until the old roof is off, and pricing as though it is all sound is how a profitable job becomes a break-even one. A unit price per sheet, written into the estimate before work starts, turns that from a surprise into something the customer already agreed to.

Layer count belongs on the sheet as a verified number rather than an assumption. Check at a rake edge or by lifting a shingle near a vent. Homeowners are genuinely unsure how many roofs are up there more often than not, and the difference changes both tear-off labor and container size.

Why pitch appears twice

Pitch corrects the area, because a footprint measurement understates a sloped surface. It also drives a labor multiplier, because anything above roughly 7/12 slows the crew and starts requiring staging and harnesses. Those are two separate adjustments and folding them into one number loses the labor half.

The full reasoning is in our guide on how to estimate a roofing job.

Repairs do not use this sheet

A repair is not a small replacement. The cost driver is access and diagnosis rather than area, and a small shingle fix carries the same setup, travel, and safety time as a much larger job. Price the trip, not the square footage, and keep repair quotes on their own short form.

For storm and insurance work, every line wants a photo attached to it, taken while you were up there. Reconstructing evidence afterward is slower and weaker. FlyQuote builds the scope from those photos so the estimate reflects the roof you inspected rather than the one you remember.